Lincoln Avenue Phase 2

Project Manager: Kelly Heath
Office Phone: (505) 896-8242
E-Mail: kheath@rrnm.gov
Contract Company: City of Rio Rancho
Cost: $  TBD
Stage: Right-of-Way Acquisition
Schedule: March 2017 - December 2017
Lincoln Ave at Adams Lane Photo
The purpose of this project is to acquire right-of-way needed for the future extension of Lincoln Avenue Phase 2 Project, which stretches from Adams Lane to Paseo del Volcan (also known as NM 347).

Additional Information:


Status Log:

  • January 2018: The City has acquired 53 parcels; additional acquisitions are on-going.
  • November 2017: All Offer Letters have been sent to property owners in the project area. The City has acquired 47 parcels; additional acquisitions are on-going.
  • September 2017: All Offer Letters have been sent to property owners in the project area. The City has acquired 8 parcels; additional acquisitions are on-going.
  • August 2017: 44 Offer Letters have been sent to property owners. 32 additional Offer Letters are pending appraisal completion and/or review.
  • June 2017: Appraisals are on-going.
  • April 2017: Appraisals are currently being prepared.
  • March 2017: Right-of-Way Mapping is complete. 
  • May 2016: Final Design Construction Plans were completed.