Neighborhood Streets Improvement Project

Project Manager: Leila Momenzadeh
Office Phone: (505) 891-5048
Email: lmomenzadeh@rrnm.gov
Contract Company: City of Rio Rancho
Cost: $ 890,000
Stage: Maintenance
Schedule: May 2017 - October 2017
NEIGHBORHOOD STREETS IMPROVEMENT PROJECT
In 2016, the Governing Body approved a resolution stating that beginning in 2017, if revenues received were higher than projected, City staff shall develop a plan to spend the unanticipated revenue to fund roadway repairs and replace equipment.
The 'Neighborhood Streets Improvement Project' will utilize these unanticipated revenues to crack seal and crack patch the neighborhood streets detailed below.

To view a map please click here.
Mobile Users: Please rotate your device to better view the table below.

District 1

Name From To Work Start
4th St SW Apache Loop Southern Blvd August
Applewood Park Dr Wexford Rd Regency Park Rd July
Archibeque Ave Arkansas St Sava Dr July
Bahama Dr Archibeque Ave Archibeque Ave July
Bermuda Dr Vancouver Rd Arkansas St July
Dennison Park Loop Applewood Park Dr Regency Park Rd August
Doral Park Rd Applewood Park Dr Regency Park Rd August
Fraser Dr Orinoco Dr Orinoco Dr August
Madeira Dr Orinoco Dr Sava Dr August
Monticello Park Dr Wexford Rd Regency Park Rd August
Nyasa Rd Pecos Loop Southern Blvd August
Orinoco Dr Archibeque Ave Fraser Dr August
Regency Park Rd End Benson Park Ct August
Rhein Dr Orinoco Dr Sava Dr August
Sava Dr Fraser Dr Archibeque Ave August

District 2

Name From To Work Start
Aspen Meadows Dr Havasu Falls St Oasis Springs Rd June
Chicoma Rd San Pedro Rd Sierra Norte Loop June
Clear Creek Pl Clear Creek Rd End June
Clear Creek Rd Camino de los Montoyas Clear Creek Ct June
Dillon Dr Minturn Loop Minturn Loop June
Gallinas Rd Acorn Loop Sierra Norte Loop June
Havasu Falls St Oasis Springs Rd Oasis Springs Rd June
Minturn Ct End Alama Dr June
Minturn Loop Colorado Mountain Rd Alama Dr June
Penasco Rd End Pine Rd July
San Pedro Rd Santa Clara Rd Chicoma Rd July
Shiloh Rd Wilpett Dr King Blvd July
Waterfall Dr Clear Creek Rd Clear Creek Rd

July

District 3

Name From To Work Start
Albany Hills Dr Augusta Hills Dr Atlanta Hills Dr Complete
Bismark Hills Way Enchanted Hills Blvd Albany Hills Dr Complete
Cabot Hills Ct End Glen Hills Dr Complete
Cibola Dr Sandoval Dr Foxmoore Dr Complete
Concord Hills Loop Albany Hills Dr Albany Hills Dr Complete
Coventry Hills Dr Freemont Hills Loop Grayson Hills Dr Complete
Freemont Hills Loop Brighton Hills Dr Brighton Hills Dr Complete
Glen Hills Dr End End Complete
Santa Fe Hills Way

Enchanted Hills Blvd Albany Hills Dr Complete

District 4

Name From To Work Start
Ashkirk Loop Greenock Dr Ashkirk Pl August
Ashkirk Pl End Ashkirk Loop August
Calle Suenos End Double Diamond Loop August
Dundee Way Ashkirk Loop Aberdeen Dr August
Foxwood Trl Double Diamond Dr Double Diamond Dr September
Inverness Dr High Resort Blvd Aberdeen Dr September
Saddlewood Trl Ridgecrest Dr Ridgecrest Dr September
Saddlewood Trl Foxwood Trl Foxwood Trl September
Saddlewood Trl Ridgecrest Dr Foxwood Trl September
White Horse Dr High Resort Blvd Newcastle Dr September

District 5

Name From To Work Start
Cathie Trl Meadowlark Ln Sara Way September
Pattys Pl Wilkes Way Sara Way September
Platina Ct Western Hills Dr End September
Platina Rd Montevine Ave Western Hills Dr September
Sara Way Wilkes Way Meadowlark Ln September
Tiffany Ln Pattys Pl Wilkes Way September
Tiffany Ln Cathie Trl Pattys Pl September
Tiffany Ln Cathie Trl Wilkes Way September
Trail Side Rd Cabezon Blvd Westside Blvd September
Western Hills Dr Caramesa Ct Platina Rd September
Western Hills Dr Rancho Plata Ave Caramesa Ct September
Western Hills Dr Rancho Oro Ave Rancho Plata Ave September
Western Hills Dr Cabezon Blvd Rancho Oro Ave September
Western Hills Dr 1013 Western Hills Dr Cabezon Blvd September
Western Hills Dr Southern Blvd 1013 Western Hills Dr September
Wilkes Way Sara Way Sara Way September

District 6

Name From To Work Start
Canadian Goose Rd Jack Rabbit Rd Cottontail Rd October
Canvasback Ct End Canvasback Rd October
Clearwater Loop Riverside Dr Clearwater Loop October
Platinum Dr Pyrite Dr Saratoga Dr October
Platinum Loop Saratoga Dr Saratoga Dr October
Talon Ct End Gray Hawk Dr October
Talon Dr Gray Hawk Dr Gray Hawk Dr October
Terrace Dr Christine Dr Denise Dr October
Whitewater Dr Honduras Rd Riverside Dr October

Why wasn’t my road selected as part of the Neighborhood Road work that is taking place now?

Crack sealing and crack patching, currently being implemented, is a treatment that is considered preventative maintenance when it is applied to roads that are in relatively good condition.  This must be done in order to prevent the roads from falling into further disrepair. 

If your road isn’t receiving repair now or isn’t on the list for this year, there are two possible reasons for this.  The first reason is that your road wasn’t selected for this phase, but could be selected next time.  There are 450 centerline miles of roads within the City, which means resources have to spread around to ensure all residents receive maintenance.  The other possibility is that the condition of your road is such where the work needed is more substantial than crack sealing and crack patching.  This more intense work would not be able to be completed by in-house City crews; therefore, it would need to bid out and the cost would be higher than the work currently being completed.